This is the Project Schedule for the Summer of 2015 – Work begins first week of July, projected to be complete at the end of August

  • Roof with new shingles
  • Replace sewer line and handicapped ramp
  • Repair gutters and downspouts
  • Exterior painting
  • Sanctuary lighting and new electric